Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Progress aganst the delivery plan as at
September 2019
The Cabinet:
1.1 Noted the Council’s performance against its Delivery Plan targets as of September 2019.
1.2 Noted that of the 82 actions, 76 actions are either complete or on target.
1.3 Noted that five actions are to have a revised due date, due in the main to external factors, and will need to go through the agreed process to revise their due date.
1.4 Noted that five projects are currently behind target, and one has not yet been started.
|
Completed |
On target |
Behind target |
Not started |
Delivery Plan actions – total 82 |
||||
32 |
44 |
5 |
1 |
Report author: Colin Cooke
Publication date: 05/12/2019
Date of decision: 03/12/2019
Decided at meeting: 03/12/2019 - Cabinet