Issue - decisions

Report on performance against our Delivery Plan – half year 2019/20

05/12/2019 - Report on Performance Against our Delivery Plan – Half Year 2019/2020

The Cabinet:

 

1.1       Noted the Council’s performance against its Delivery Plan targets as of September 2019.

 

1.2       Noted that of the 82 actions, 76 actions are either complete or on target.

 

1.3       Noted that five actions are to have a revised due date, due in the main to external factors, and will need to go through the agreed process to revise their due date.

 

1.4       Noted that five projects are currently behind target, and one has not yet been started. 

 

 

Completed

On target

Behind target

Not started

Delivery Plan actions – total 82

32

44

5

1